Enter Progress Information in the Spreadsheet View
Use this procedure to enter progress information in spreadsheet view.
To enter activity progress information in a spreadsheet view:
- Assign the Progress Spreadsheet view to your project by dragging the Progress Spreadsheet file from the Views folder in the Open Plan Library onto your project.
- Open the Progress Spreadsheet view of your project.
-
For each activity for which you want to enter progress information, enter actuals data using the following columns:
- Actual Start: Date on which an activity was started.
- Actual Finish: Date on which an activity was completed.
-
Progress Type: You can select from the following progress types:
- Complete
- Elapsed Duration
- Percent Complete
- Planned
- Remaining Duration
The value you select in this field determines how Open Plan interprets the Progress Value.
- Progress Value: The value you enter in this field depends on your selection in the
Progress Type column:
- If you have selected either Complete or Planned in the Progress Type column, leave this field blank.
- If you have selected Elapsed Duration, Percent Complete, or Remaining Duration in the Progress Type column, enter the appropriate value in this field.
Parent Topic: Spreadsheet View