Enter Progress Information in a Dialog Box

Use this procedure to enter progress information in a dialog box.

To enter activity progress information in a dialog box:

  1. Select the appropriate activity, and click Progress on the Edit tab.
  2. On the Activity tab of the Activity Progress dialog box, enter the progress information for the activity.
    For example, you might enter an actual start and actual finish date if the activity is complete, or you might enter an actual start date and an expected finish date if the activity is in progress.
  3. Click Apply.