Display the Resource Scheduling Dialog Box

Use this procedure to display the Resource Scheduling dialog box.

To display the Resource Scheduling dialog box for a project that contains resource assignments:

  1. In Open Plan Explorer, select a project.
  2. Take one of the following actions:
    • Right-click the selected project, and click Resource Scheduling from the context menu.
    • Click the arrow under Resources in the Schedule menu group of the Processes tab, and click Options.
    It is not necessary for the project to be open.