Display the Project Start Date Dialog Box
Use this procedure to display the Project Start Date dialog box.
To display the Project Start Date dialog box:
- Open a project.
- On the Processes tab, select Baselines from the Dialogs menu group.
- In the Baselines dialog box, click New.
- In the Add Baseline dialog box, enter a Name and Description.
- Enable Ignore Progress, Use Original Project Start Date and then click OK.
- Select the date and then click OK.
- When prompted to select it as the new baseline, select either Yes or No, as appropriate.
Parent Topic: Project Start Date Dialog Box