Display the Cost Calculations Dialog Box

Use this procedure to display the Cost Calculations dialog box.

To display the Cost Calculations dialog box:

  1. Take one of the following actions:
    • Select the project in Open Plan Explorer, and click Cost on the Processes tab in the Calculate menu group.
    • Right-click the project in Open Plan Explorer and click Cost Calculations on the shortcut menu.
    Note: It is not necessary for the project to be open.