Display the Copy Baseline Dialog Box
Use this procedure to display the Copy Baseline dialog box.
To display the Copy Baseline dialog box:
- In the Project Views folder of Open Plan Explorer, display a project in any view.
- On the Processes tab, select Baselines from the Dialogs menu group.
- In the Baselines dialog box, select the baseline you want to copy and then click Copy.
You can also display the Baselines dialog box by clicking Select Baseline on the Summary tab of the Project Properties dialog box.