Define Access Rights to a Baseline
Use this procedure to define the access rights to a baseline.
Note: You must be the owner of the baseline or have SYSADMIN rights to define access rights to it.
To define the access rights to a baseline:
- In the Project Views folder of Open Plan Explorer, display a project in any view.
- On the Processes tab, select Baselines from the Dialogs menu group.
- In the Baselines dialog box, select a baseline and then click Access Control.
- In the Baseline Access Control dialog box, assign access rights to the baseline.
- When finished, click OK.
You can also display the Baselines dialog box by clicking Select Baseline on the Summary tab of the Project Properties dialog box.
Related Topic
Parent Topic: Related Procedures