Contents of the Cost Calculations Dialog Box
Use the fields and options to configure the Cost Calculations dialog box.
Contents
| Field | Description |
|---|---|
| Budget Cost | This option controls whether Open Plan should calculate the budgeted costs for the resources assigned to each activity in the project. When this option is selected, Open Plan populates the following fields on the activity table:
|
| Based On Dates | If you select Budget Cost or Remaining Cost, you can also select whether calculations should be based on early dates, late dates, or scheduled dates. |
| Remaining Cost | This option controls whether Open Plan should calculate the remaining costs for resources that are assigned to each progressed activity in the project.
Open Plan calculates remaining costs for only those resources that have the Progress Based on Activity Progress option selected in the Resource Details dialog box. When this option is selected, Open Plan populates the following fields on the activity table:
|
| Actual Cost | This option controls whether Open Plan should calculate the actual costs for resources that are assigned to each progressed activity in the project.
Open Plan calculates actual costs for only those resources that have the Actual Cost Based on Progressed Quantity option selected in the Resource Details dialog box. When this option is selected, Open Plan populates the following fields on the activity table:
|
| Earned Value (BCWP and BCWS) | A cost control that allows you to quantify the overall progress of the project in monetary terms. Earned value is calculated by multiplying the physical percent complete by the planned cost. Another term for earned value is budgeted cost of work performed (BCWP). |
| Use Resource Cost Escalation | This option controls whether Open Plan should use escalated or unescalated resource costs when calculating costs.
|
| Include Child Activity Values in Subproject Costs | This option controls whether Open Plan should roll child activity costs up to the subproject level:
|
| Time Analyze Before Cost Calculation | When this option is selected, Open Plan performs Time Analysis before calculating costs. |
Parent Topic: Cost Calculations Dialog Box