Add a Child Activity (Spreadsheet View)

When you add a child in a spreadsheet view, Open Plan automatically converts the parent activity into an internal subproject.

To add a child activity:

  1. In the Project Views folder of Open Plan Explorer, select a project to display in spreadsheet view.
  2. Create an activity with an ID that indicates the desired parent/child relationship.
    For example, to add a child to activity ACT01, create activities ACT01.01, ACT01.02, and so on.