Activity and Relationship Calendars

You can specify both a default activity calendar and a default relationship calendar on the Preferences tab of the Project Properties dialog box.

To specify the calendars, use the following fields:

  • Def. Activity Calendar: This field is used to specify that an existing calendar is to be used as the default calendar for new activities.
  • Def. Relationship Calendar: This field is used to specify that an existing calendar is to be used as the default calendar for new relationships.