Enable Actuals in Resource Allocation Component

Use these steps to enable actuals in the resource allocation component.

To enable this feature:

  1. Go to System Setup > Parameters and Numbers > System Parameters.
  2. Double-click the Update Actuals on Job Budget Line Resources parameter.
  3. On the System Parameter sub-tab, select the Update Actuals on Job Budget Line Resources check box.
  4. Click Save.
  5. Double-click the Use Estimate Date when Updating Resource Allocations parameter.
  6. On the System Parameter subtab, select the Use Estimate Date when Updating Resource Allocations check box.
  7. Click Save.