Revise Estimate-To-Complete Subtask

Use this subtask to revise your Est-to-Compl hours for the selected project by subtracting incurred hours from budget hours.

Alternatively, you can revise your Est-to-Compl by entering a contract percent complete. Est-to-Compl and LREAC hours are automatically updated. If you want to revise ETC information for a range of projects, use the Compute Estimate to Complete screen instead of this subtask.

Run this utility any time after you run the Update Incurred Cost for ETC screen. If you select the Update ETC with Budget Minus Incurred option, you must enter project total budgets as well.

Revision Type

Field Description
Update ETC with Budget Minus Incurred

Select this option to identify the LREAC amount as the project total budget. Costpoint subtracts ITD project costs incurred from the budget to arrive at Est-to-Compl hours.

Update LREAC with Percent Complete

Select this option to enter a Percent Complete. Costpoint multiplies actual hours incurred by GLC by this percent to arrive at LREAC hours. Actual hours for all GLCs are multiplied by this percent. Est-to-Compl hours are the difference between the LREAC and actual hours incurred.

Percent Complete

If you selected the Update LREAC with Percent Complete option, enter the percentage complete in this field.

Update

Field Description
Update Dates

Select this check box to update the fields in the Date Updated group box in the main screen for the selected project.

Update Previous Estimate

Select this check box to update the Prev EAC and Prev % Compl fields in the main screen for the selected project.

Revise ETC

Click this button to revise the ETC.