You are here: Ajera Help (A-Z) > dashboards > Widget Bases > Project Progress Base

Project Progress Base

unavailable in ajeraCore

Use this widget to help you determine if a project is on time and on budget. You can compare the amount you spent on your project against the budgeted amount and the reported percent complete amount on a project-to-date basis.

Available Columns Description Date Range Available Chartable Links to Page
General Information
Display Date

The start date of the project or the first date effort was expended on the project, whichever is earlier.

This column lists the weeks or months (weeks if the project is less than 121 days) for the duration of the project.

     
Dollars
Contract The amount contracted to be spent on the project as of the date listed      
RPC % The most recent reported percent complete, as entered on the Manage tab      
RPC The reported percent complete on the project as of the date listed multiplied by the contract amount      
RPCSpent Diff Indicates if you are on track with budget, if you spent more or less than expected      
Spent The amount you spent on the project as of the date listed.      
Keys
Phase Key The database identifier of the phase      
Project Key The database identifier of the project      

 

 

 

© 2024 Deltek Inc. All rights reserved.