When progress has been submitted and approved in PM Compass, you can see the changes in the Schedule Analysis view. PM Compass performs several steps to include the changes in the Primavera P6 schedule.
Check for progress |
Related Topics |
When the nightly schedule process runs, it checks to see if there is any new progress that must be added to the Primavera P6 schedule. If there is no new progress, this step is skipped. If there is progress, PM Compass exports the progress and updates the fields in the Primavera P6 schedule. The process runs as a scheduled process or when you click Run Now on the Schedule Integration tab. The system uses the Primavera P6 Object ID field to find the activity to update in Primavera P6. Only the following status fields are updated in the Primavera P6 schedule:
When Remaining Duration is updated, Primavera P6 automatically calculates the Activity % Complete, Duration % Complete, and Performance % Complete fields. If the progress type is Percent Complete, the progress value returned is the Duration % Complete. The numerous Unit and Cost Percent Complete fields are automatically calculated by Primavera P6 when the Resource Assignment Physical % Complete or the Remaining Units is updated. In addition to the status fields, if the fields in the Last Progress Submission Date Fields group on the Projects Form Progress tab in PM Compass are populated, that information is also updated in Primavera P6. If the process fails, an email is sent to the person who scheduled the process to let them know that an error occurred. They can do one of the following:
If the process completes with nonfatal errors, an email is sent to the person who scheduled the process, letting them know about the error and providing a hyperlink to the process log. The progress entry that caused the error is skipped and all other progress entries are exported. View the Data that was Exported to Primavera P6If you have a copy of Open Plan and you want to review the data that was exported to Primavera P6, you can add a setting (_KEEP_P6_OUTPUT_FILES) to the Open Plan System Preferences dialog box so that Open Plan creates .csv integration files. For more information and steps, see View Data that was Exported to Primavera P6 in Related Topics. |
How to...View Data that was Exported to Primavera P6 Specify the Source System Note Category Learn more about...Primavera P6 to PM Compass Field Mapping General Tab of the Schedule Analysis View |
Reschedule work |
After progress has been updated in the Primavera P6 schedule, the Primavera P6 Schedule process reschedules the uncompleted work to begin after Period End Date. This allows the subsequent import into PM Compass to display the new dates calculated by Primavera P6. |
Load the Primavera P6 project into PM Compass |
Related Topics |
After the Primavera P6 schedule has been updated and the Schedule process has run, and there are no errors (if any part of the export fails, then the import won’t start), the updated Primavera P6 project is loaded into PM Compass. The various progress types are used to calculate the remaining duration which is then exported to Primavera P6. When the progress is imported back into PM Compass, the progress type is retained. There are two exceptions:
If the process fails, an email is sent to the person who scheduled the process, letting them know about the error and providing a hyperlink to the process log. No email is sent if the process was scheduled and no errors occur. Log FilesAfter the Primavera P6 project has been loaded into PM Compass, log files are generated to indicate any errors or warnings that were encountered during the process. |
Learn more about...How PM Compass Calculates % Complete to Export to Primavera P6 |