Primavera P6 Constraints

Primavera P6 allows an activity to have both a primary and a secondary constraint and date. PM Compass permits both types of constraints on the same activity as long as the P6 constraints are not both start or finish constraints (that is, one must be a start, and the other must be a finish constraint).

Primavera P6 Constraint

PM Compass Constraint

As late as possible (ALAP)

Activity type = As late as possible (ALAP)"

Finish on or after

Target finish = not earlier than

Start on or after

Target start = not earlier than

Start on

Target start = on target

Mandatory start

Target start = fixed target

Finish on

Target finish = on target

Mandatory finish

Target finish = Fixed target

Start on or before

Target start = not later than

Finish on or before

Target finish = not later than