Create New Cost Sets in Cobra

Using Cobra, go to the Cost Sets Tab of the Project Information Dialog Box to add and delete custom cost sets and to update the description or the included classes for a standard cost set.

To create a new cost set:

  1. Display the Cost Sets tab of the Project Information dialog box by completing one of the following steps:

  2. In Cobra Explorer, double-click a project name on the Projects pane, and click  . On the Project Information dialog box, select the Cost Sets tab.

  3. In Cobra Explorer, select the Projects group bar, right-click a project on the Projects pane, and select Project Information from the shortcut menu. On the Project Information dialog box, select the Cost Sets tab.

  1. On the Cost Sets tab, click New to insert a new row on the left grid.

  2. Enter the name and description for the new cost set.

  3. Click OK.