This tab displays milestones or steps under the work package. The columns for this tab depends on the selected EVT for the work package.
Option |
Description |
Milestones |
Select one of the following options from this drop-down list:
|
This table lists the default columns for the Milestone, Earning Rules, and Steps EVT.
Field Name |
Description |
Milestone |
This column displays the unique ID of the milestone. |
Description |
This column displays the milestone description. |
Baseline Finish |
This column displays the baseline finish date for the milestone. You cannot modify the date in this column. This column is not available if the EVT is Earning Rules or Steps. |
Actual Finish |
This column displays the actual finish date for the milestone. You can modify the date in this column but the new date must not be later than the status date. This column is not available if the EVT is Earning Rules or Steps. |
Forecast Finish |
This column displays the forecast finish date for the milestone. You can modify the date in this column if there is no date specified in the Actual Finish column for the milestone. This column is not available if the EVT is Earning Rules or Steps. |
Status |
This column displays whether the milestone is In-progress, Planned, or Completed. Entering a date in the Actual Finish column automatically changes the milestone's status to Completed. |
Weight |
This column displays the weight of the milestone that will sum up to the work package. The total weight of the milestones for a work package is 100. |
% Complete |
This column displays how much of the milestone has been completed in percent. This column is available only if the Allow percent complete on milestones/steps option is selected on the Preferences tab of the Project Information dialog box in Cobra. |
Completed |
An unmarked check box in this column indicates that the milestone status is either In-progress or Planned. Marking the checkbox changes the milestone status to Completed. This column is not available if the Allow percent complete on milestones/steps option is selected on the Preferences tab of the Project Information dialog box in Cobra. |
Find control accounts or work packages that are not progressing according to plan
Enter progress for a Progress entry that is not displayed
View explanation of variance for a control account or work package
View time phased resource data for a control account or work package