Open Plan PM Compass Change Requests Add-In Overview

When a PM Compass project is integrated with a schedule, the change request typically involves changing the schedule. When a change request such as adding activities to the schedule, or other changes such as the addition of resource assignments or changes to relationships are made, the live project is not updated until the change request is approved. Instead, changes entered are stored in a temporary (sandbox) project and applied to the current database through the Open Plan PM Compass Change Requests Add-In.  

When the change is approved, PM Compass updates the current schedule. Only those fields affected by the change request are updated. Thus, if the schedule has changed since the workflow was created and the change details entered, when the change is approved, those changes are applied to the updated schedule.  

A user must be a SYSADMIN or belong to a group in order to have access to the Add-In.

Example

Assume a change request is for the addition of a new resource assignment on an activity. Since the workflow was created, the duration on the activity has increased and a relationship has been added. When the change is approved using the Add-In, the entire activity in the change request is not copied to the schedule; that would overwrite the subsequent changes. Instead, only the actual changes that were made are applied. In this example, the resource assignment is added to the activity. The new duration and relationship are not affected.  

The PM Compass Change Requests Add-In

Using the PM Compass Change Requests Add-In to approve a change request has a number of advantages:

A workflow without a schedule attached must be approved in PM Compass to advance the workflow to the next step.