This topic outlines the Cobra configuration file settings for a Change Request. These settings ensure that Change Request costs are correctly imported into Cobra. The configuration file is set up using the Cobra Integration Wizard.
Part of the change request process is using Cobra's Integration Wizard, called through the API and web services, to load data from the Open Plan schedule into Cobra. Some of the settings are defined in the wizard and some are overwritten based on options you select on the Change Details on Form tab in Workflow Type Configuration. This allows you to configure options such as how your project is linked to the schedule as well as your change control options. These configurations are set in Workflow Type Configuration for each change request type.
When a process such as the Integration Wizard is run, Cobra writes error and warning messages to a log. You can view the log from the change request Links tab.
This feature is only enabled if Cobra is configured to write process logs to a file. See Configure Cobra to Write Process Logs to a File for steps on setting this up and for information about the file name.
To set up the integration file for the change request process using the Cobra Integration Wizard, complete the following steps:
In Cobra, click the Integration tab.
In the Import group, click the project to which you are integrating (Open Plan or MS Project).
On the Integration Configuration page, in the Where are you loading the data from? drop-down list, select the product to which you are integrating (Open Plan, Microsoft Project, or Microsoft Project Server.
On the Action Selection page, under the Project Data heading, select:
Control Account and Work Package
Resource Assignments
Code Assignments — You can select this option if your project is linked to code assignments.
On the Project Selection page, PM Compass overrides the Schedule Project and Cobra Project fields based on the project selected in the change request. You need to select a project that uses the same field mappings with the schedule as the one you intend to select in the change request. All projects with the same field configuration and schedule mapping can use a single change request type; however, if you have some projects with different configurations (for example, some have three key fields and some have two key fields), you will need to create separate integration files and change request types for each project configuration and schedule mapping.
The settings on the Date Selection page are overridden to match what is defined in Workflow Type Configuration. You should select to load both budget and forecast as well as Baseline Dates so that the remainder of the Integration Wizard pages allow you to select the proper fields.
Use the Schedule Mapping page to link your project to the schedule based on your configuration settings.
On the Earned Value page, select your preferred settings for how the earned value technique will be created.
On the Resource Assignments page, select the following settings:
For a Budget Change request, select Budget Group Box — Load budget class from field: Cost Class (Assignment)
For a Forecast Change Request, select Forecast Group Box — Add to existing forecast
If a Budget Change Request has the Update the Forecast with the Budget Change option on the Change Details on Form tab of Workflow Type Configuration selected, you must select the following settings:
Forecast Group Box
Add to existing forecast
Load all forecast into default class
On the Change Control page, select the settings that suit your setup.
Selecting the following options will apply all changes in the Change Details view to the live Cobra project:
Force existing Work Package baseline dates to match the schedule
Update Control Account dates to span Work Package dates exactly
Update the description for existing Control Accounts and Work Packages
If you select Apply historical <budget/forecast> changes as an adjusting entry in the current status period, an adjusting entry may be performed in the current period. See Complete a Change When the Calendar Has Been Advanced for more information.
Complete the Integration Wizard, saving your configuration.
In PM Compass, enter the configuration file name in the Schedule Integration Configuration field on the Change Details on Form tab of Workflow Type Configuration.
When the scheduler approves a change request, the Cost System Process step action starts the schedule integration process. The process runs Cobra's API which calls the Integration Wizard using the file selected in the Schedule Integration Configuration.
To confirm the configuration is setup correctly, complete the following steps:
Create a workflow and select your project.
In the Change Details view, make at least one schedule change.
After approving the change request in the Open Plan add-in, click Tools » Process Logs and make the following selections:
Project — The project selected in the change request
Process — Integration Project Data
Check Show All Users
Click the Start column to sort the processes so that the most recent is at the top
Open the process log and confirm that your change was loaded.
Cancel the change request you just created to delete all temporary data and not affect the live projects.
Make Cobra projects visible in PM Compass
Learn about the change management process
Run a Cobra report on a change request