Edit Date Properties
Use the Edit Date Properties Subtask to modify work schedule properties for Resources you manage.
To modify work schedule properties for specific dates, complete the following steps:
-
Click Time & Expense > Time > Timesheets > Manage Resource Work Schedules to display the Manage Resource Work Schedules screen.
-
In the Month/Year field, click
to select the month that contains the date you want to modify. -
Click
to populate the Month/Year results table with that month/year. -
In the Month/Year results table, select the date you want to modify and click the Edit Date Properties subtask link.
-
In the Edit Date Properties subtask, modify the desired fields and, when you are finished, click
.NOTE. The subtask displays dates for only one week at a time. If you want to edit a day in a different week, select that date in the Month/Year results table and reopen the subtask.