Burdened Labor and ODC’s Report
The Burdened Labor and ODC's report displays the burdened costs by resource for labor and by account for non-labor, by project. You must be licensed for COBRA to use this report.
This report uses specific tables, which need to be created by a specific process in Costpoint, relating to Deltek Cobra integration.
A project is identified as a Cobra program by selecting the Cobra Program checkbox on the Manage Project User Flow screen in Costpoint. This option is visible if you are licensed for COBRA and can only be selected at the top level of the project. If selected, the entire project tree will be included in the Compute Cobra Burden Costs process.
Related Topics:
Use the Burdened Labor and ODC's prompts to configure the report.
View a sample of the Burdened Labor and ODC's report.