You must specify the CV and SV values in the appropriate work packages as PM Compass does not calculate them.
To specify the reprogramming adjustments for CV and SV:
-
Display the Project Properties dialog box.
-
On the Classes tab, create new budget classes to hold the CV and SV values.
-
On the Cost Sets tab, create the ReprogCVA and ReprogSVA cost sets, and add the classes you created to these cost sets.
For example, if you created a class named CV, add the CV class to the ReprogCVA cost set. Similarly, do the same for the SV cost set.
-
In the project, manually add the CV and SV values to the work packages where you want to display in the Reprogramming Adjustments section of the IPMR CPR Format 1 report and in the IPMDAR export.