Use this procedure to enable time-phased data logging and designate if baseline changes are significant or not, for the purpose of collecting data for the IPMR Format 3 report.
To enable time-phased data logging:
-
Display the Project Audit Wizard.
-
On the Log Operation page, do the following:
- Select the
Turn Log On option.
- Select the
Log time-phased changes option.
-
Complete the pages of the Project Audit Wizard to enable time-phased data logging.
Note: If the project log is already turned on prior to selecting the
Log time-phased changes option you need to turn off the project log first.