Project Progress Base
unavailable in ajeraCore
Use this widget to help you determine if a project is on time and on budget. You can compare the amount you spent on your project against the budgeted amount and the reported percent complete amount on a project-to-date basis.
Available Columns | Description | Date Range Available | Chartable | Links to Page |
General Information | ||||
Display Date |
The start date of the project or the first date effort was expended on the project, whichever is earlier. This column lists the weeks or months (weeks if the project is less than 121 days) for the duration of the project. |
|||
Dollars | ||||
Contract | The amount contracted to be spent on the project as of the date listed | |||
RPC % | The most recent reported percent complete, as entered on the Manage tab | |||
RPC | The reported percent complete on the project as of the date listed multiplied by the contract amount | |||
RPCSpent Diff | Indicates if you are on track with budget, if you spent more or less than expected | |||
Spent | The amount you spent on the project as of the date listed. | |||
Keys | ||||
Phase Key | The database identifier of the phase | |||
Project Key | The database identifier of the project |