Changing tasks for a project
Project managers, or other employees with proper security access, can change tasks on a project.
unavailable in ajeraCore
To change tasks for a project
- If you are not already working with the project, open it by clicking it in the project list at the top of the Project Command Center.
- Click the Manage tab.
- Select the Show task rows check box located above the table.
- To see resources (especially if you later want to change tasks for them), select the Show resource rows check box also located above the table.
- To show or hide a column, click (Customize) and select the columns.
- Change information for a task, as needed.
For |
You can change |
---|---|
Type |
The type of employee. Click the field, click , and make a selection. |
Resource |
The employee who performs the work. Click the field, click , and make a selection. |
Reference |
The short description that helps you further identify the task |
Status |
The status of the task (such as if the task is not started, in progress, or complete). Click the field, click , and make a selection. |
Priority |
The task's level of importance (low, medium, or high). Click the field, click , and make a selection. |
Hours |
The number of hours you estimate are needed to complete the task |
% complete |
The percent of work that is complete, if any |
% complete date |
If you entered a % of work complete, change the date when you are reporting that percent of work is complete. |
Est start date |
The date when you expect the task to begin |
Est completion date |
The date when you expect the task to be complete |
Start date |
The date when work begins on the task |
Completion date |
The date when work for the task is complete |
Notes |
The notes about the task |
- Change other tasks in the same way.
- Click Save.
Note: |
To print or inquire on the information, select an inquiry from |