Time & Expense List window (Tasks by Employee tab)
unavailable in ajeraCore
Field | Description |
---|---|
Employee |
The employee assigned to the task |
Description |
The name of the task |
Optional columns: |
|
First name |
The employee's first name. To sort the list by first name, click the heading for this column. |
Middle name |
The employee's middle name. To sort the list by middle name, click the heading for this column. |
Last name |
The employee's last name. To sort the list by last name, click the heading for this column. |
Project |
The project associated with the task |
Phase |
The phase associated with the task |
Employee type |
The type of employee who performs the task, such as Architect |
Reference |
Any additional information which further identifies or describes the task |
Status |
The status of the task |
Priority |
The task's level of importance as either low, medium, or high |
Hours |
The number of estimated hours assigned to complete the task |
% complete |
The percent of the task that is complete |
% complete date |
If you entered a percent complete, the date that you entered it |
Est start date |
The date when work on the task is expected to begin |
Est completion date |
The date when work on the task is expected to be complete |
Start date |
The date when work on the task actually begins |
Completion date |
The date when work on the task is actually complete |
Notes |
Any notes about the task |
Any attachments related to the item You can click the attachments icon in the table to add, change, or open attachments. The column displays |