Fields on the upper right of the Planning tab display multiplier and currency information. Currency is only relevant if you use the Vision Multicurrency feature. All chart and grid information displays in the selected currency.
Contents
The
EAC Multiplier
updates when a project, phase, or task is selected on the Planning grid.
The calculations for the data are as follows:
| Field | Description |
| Target Multiplier
|
If you are viewing a Vision plan, this field displays the Target Multiplier for Cost from the General tab of Vision Project Planning. If you are viewing a Navigator plan, this field displays the
Target Multiplier that is assigned in Plan Settings. This multiplier is used as the basis for evaluation against the EAC multiplier. The multiplier represents how much revenue is anticipated for each labor cost dollar spent on a project.
If the Vision plan's
Budget Type
is set to Billing, the multiplier is blank. If the Vision plan's
Budget Type is set to Cost, or
Cost and Billing, you can assign a target multiplier for cost in Vision Project Planning.
Calculation: Target Multiplier = Cost Target Multiplier
If a project is mapped to multiple Vision plans that have the
Include in utilization and project reports option selected, Navigator uses the target multiplier from the plan with the earliest creation date.
|
| EAC Multiplier
|
The estimate-at-completion (EAC) labor cost amount is the cost value of the hours worked through today and the remaining planned hours. The EAC multiplier is the contract amount for the project divided by the Labor EAC Cost.
All Navigator plans are marked to
Include in utilization and project reports. Vision plans may or may not be marked to
Include in utilization and project reports.
The job-to-date values in EAC are from posted and unposted labor. If a plan's budget type is set to
Billing, the plan does not track cost values and nothing can be calculated for the EAC cost multiplier.
Calculation: EAC Multiplier = Contract Amount/EAC Labor Cost Amount
The following example shows a calculation in which a project is mapped to multiple Vision plans:
- Project X is mapped on three plans.
- Each plan has
Include in utilization and project reports selected.
- The project has $500 of JTD labor at cost through 5/31/2014.
- The project has $1000 of ETC labor cost amount as of 6/1/2014 on each plan.
- The project has $5000 for the Contract Amount.
The EAC Multiplier calculation for Project X is as follows:
5000 / (1000+1000+1000+500)=1.43
Navigator displays $5000 in the
Contract field and $3500 in the
Estimate at Completion field for Project X as of 5/31/2014 (today's date in the example).
|
| Currency
|
If your firm uses Vision Multicurrency, this field displays the currency code. The currency code is based on the
Use Billing Currency not Project Currency option in Vision Accounting System Settings.
|