How Vision Navigator Spreads Amounts Across the Resource Calendar

Vision Navigator calculates and spreads hours across the calendar periods and rows in the Resource Assignments grid.

When you enter hours for a resource in the ETC field in the summary or calendar view, Navigator spreads the hours evenly across working days in each calendar period shown. The calendar periods are based on the WBS element's date range and the calendar scale that is selected in Project Settings.

The calculations are as follows: