Schedule a Variance Run

For optimal performance and minimal impact on Planning users, Deltek strongly recommends that you schedule variances during non-business hours.

To schedule a variance run, complete the following steps:

  1. From the Vision Navigation menu, click Planning > Spread Variance.
  2. On the toolbar, click Schedule to display the Schedule dialog box.
  3. Complete the fields on the Main tab, Recurrence tab, and Parameters tab of the Schedule dialog box.
  4. Click OK. The Spread Variance feature does not apply to the following types of plans:
    • Plans containing dependent tasks (from the Schedule tab of Project Planning)
    • iAccess for Vision plans