Schedule the Consolidation Process to Run at Another Time

You can schedule the consolidation process to run at a later time.

To schedule the consolidation process to run at a later time, complete the following steps:

  1. From the Vision Navigation menu, click Accounting > Consolidations.
  2. In the Range of Periods fields on the Consolidations form, select the beginning and ending accounting periods for which you want to consolidate data.
  3. In the list of groups, select the consolidation groups for which you want to run the consolidation process.
  4. Click Schedule. Vision displays a message that asks if you are sure that you want to proceed.
  5. Click Yes to continue.
  6. On the Schedule dialog box, select a processing queue, enter a description, and specify the date and time that you want the consolidation process to run.
  7. Click OK.
After the consolidation process completes, you can run consolidated general ledger reports for the consolidation groups that you processed.