Projects Table Formats (PR)

Follow Vision specifications for preparing a file containing project data.

Field Name Data Type Length Notes
WBS1 varchar 30 Project number; primary key
WBS2 varchar 7 Reference field for the project phase; this column is populated by Vision after the WBS1 column in this table is filled in; primary key; must have at least one blank space
WBS3 varchar 7 Reference field for the project task; this column is populated by Vision after the WBS1 column in this table is filled in; primary key; must have at least one blank space
Name varchar 40 Project name; required field
ChargeType varchar 1 Variable indicating the project's charge type; required field; must exist in CFGChargeType (Type/Label)

Valid options are:

SubLevel varchar 1 Variable indicating whether or not the project has phases and tasks; default is N (No)
Principal varchar 20 Principal's employee number; must exist in EM
ProjMgr varchar 20 Project manager's employee number; must exist in EM
Supervisor varchar 20 Project, phase, or task supervisor's employee number; must exist in EM
ClientID varchar 32 Client number; must exist in CL (ClientID/Client)
CLAddress varchar 20 Client address code; must exist in CLAddress
Fee decimal 19,4 Sum of fees for direct labor and direct expense in project currency; cannot enter unless ChargeType = R and Sublevel = N
FeeBillingCurrency decimal 19,4 Sum of fees for direct labor and direct expense in billing currency; cannot enter unless ChargeType = R and Sublevel = N
FeeFunctionalCurrency decimal 19,4 Sum of fees for direct labor and direct expense in functional currency; cannot enter unless ChargeType = R and Sublevel = N
FeeDirLab decimal 19,4 Project's fee for direct labor in project currency; cannot enter unless ChargeType = R and Sublevel = N
FeeDirLabBillingCurrency decimal 19,4 Project's fee for direct labor in billing currency; cannot enter unless ChargeType = R and Sublevel = N
FeeDirLabFunctionalCurrency decimal 19,4 Project's fee for direct labor in functional currency; cannot enter unless ChargeType = R and Sublevel = N
FeeDirExp decimal 19,4 Project's fee for direct expense in project currency; cannot enter unless ChargeType = R and Sublevel = N
FeeDirExpBillingCurrency decimal 19,4 Project's fee for direct expense in billing currency; cannot enter unless ChargeType = R and Sublevel = N
FeeDirExpFunctionalCurrency decimal 19,4 Project's fee for direct expense in functional currency; cannot enter unless ChargeType = R and Sublevel = N
ConsultFee decimal 19,4 Project's direct consultant fee in project currency; cannot enter unless ChargeType = R and Sublevel = N
ConsultFeeBillingCurrency decimal 19,4 Project's direct consultant fee in billing currency; cannot enter unless ChargeType = R and Sublevel = N
ConsultFeeFunctionalCurrency decimal 19,4 Project's direct consultant fee in functional currency; cannot enter unless ChargeType = R and Sublevel = N
ReimbAllow decimal 19,4 Project's reimbursable allowance in project currency; cannot enter unless ChargeType = R and Sublevel = N
ReimbAllowBillingCurrency decimal 19,4 Project's reimbursable allowance in billing currency; cannot enter unless ChargeType = R and Sublevel = N
ReimbAllowFunctionalCurrency decimal 19,4 Project's reimbursable allowance in functional currency; cannot enter unless ChargeType = R and Sublevel = N
ReimbAllowExp decimal 19,4 Project's reimbursable allowance for expenses in project currency; cannot enter unless ChargeType = R and Sublevel = N
ReimbAllowExpBillingCurrency decimal 19,4 Project's reimbursable allowance for expenses in billing currency; cannot enter unless ChargeType = R and Sublevel = N
ReimbAllowExpFunctionalCurrency decimal 19,4 Project's reimbursable allowance for expenses in functional currency; cannot enter unless ChargeType = R and Sublevel = N
ReimbAllowCons decimal 19,4 Project's reimbursable allowance for consultants in project currency; cannot enter unless ChargeType = R and Sublevel = N
ReimbAllowConsBillingCurrency decimal 19,4 Project's reimbursable allowance for consultants in billing currency; cannot enter unless ChargeType = R and Sublevel = N
ReimbAllowConsFunctionalCurrency decimal 19,4 Project's reimbursable allowance for consultants in functional currency; cannot enter unless ChargeType = R and Sublevel = N
BudOHRate decimal 9 Project's budgeted overhead rate; cannot enter unless ChargeType = R and Sublevel = N
Status varchar 1 Project's status; valid options are A (Active), I (Inactive), or D (Dormant); required field; must exist in CFGProjectStatus (Code/Description)
RevType varchar 10 Project's revenue method; must exist in CFGRGMethods (Method/Description); cannot enter unless ChargeType = R and Sublevel = N
MultAmt decimal 9 Multiplier or amount to use for the project when running Revenue Generation; cannot enter unless ChargeType = R and Sublevel = N
Org varchar 14 Project's organization; must exist in Organization
UnitTable varchar 20 Default unit table to use for the project; must exist in UnitTable
StartDate datetime 8 Expected start date for the project
EndDate datetime 8 Expected end date for the project
PctComp decimal 9 Estimated overall percent complete for the project
LabPctComp decimal 9 Estimated labor percent complete for the project
ExpPctComp decimal 9 Estimated expense percent complete for the project
BillByDefault varchar 1 Variable indicating whether or not certain project expenses are billable to the client. Valid options are Y (Yes, Billable), N (No, Nonbillable), or C (Category-specific)
BillableWarning varchar 1 Type of message to display in Expense when the user charges certain expenses to the project; valid options are E (Error), W (Warning), or N (None)
Memo text 16 Memo field for comments on the project
BudgetedFlag varchar 1 Budgeted labor code check for timesheets. Valid options are N (None), W (Warning), or E (Error)
BudgetedLevels varchar 5 Project's budgeted labor code levels; used when budgeted validation is in effect for timesheets
BillWBS1 varchar 30 Reference project for the Unbilled Detail Report
BillWBS2 varchar 7 Reference field for the project phase
BillWBS3 varchar 7 Reference field for the project task
XCharge varchar 1 Setting to use for cross charges to the project; valid options are G (Global, default), N (None), or P (Project)
XChargeMethod smallint 2 Cross-charge method for the project; valid options are 1 (Billing Terms) or 0 (Multiplier)
XChargeMult decimal 9 Cross-charge multiplier for the project
Closed int 4 Reserved for future use
ReadOnly int 4 Reserved for future use
DefaultEffortDriven int 4 Reserved for future use
DefaultTaskType int 4 Reserved for future use
VersionID int 4 Reserved for future use
ContactID varchar 32 Contact record number for the primary contact; must exist in Contacts (ContactID/(LastName,FirstName,MiddleName,ClientID/Client))
CLBillingAddr varchar 20 Client's billing address; must exist in CLAddress
LongName varchar 255 Project's long name
Address1 varchar 50 First line of the project's address
Address2 varchar 50 Second line of the project's address
Address3 varchar 50 Third line of the project's address
City varchar 30 City of the project's address
State varchar 10 State of the project's address.

The state must exist in CFGStates. If you import both state and country, that combination must already be a valid combination in Vision. If you import a state but not a country, the state must be a valid state for the United States.

Zip varchar 10 ZIP code of the project's address
County varchar 50 County of the project's address
Country varchar 40 Country of the project's address
FederalInd varchar 1 Variable indicating whether or not this is a federal project; default is N (No)
ProjectType varchar 10 Project type; must exist in CFGProjectType (Code/Description)
Responsibility varchar 10 Organization's project responsibility; must exist in CFGPRResponsibility (Code/Description)
Referable varchar 1 Variable indicating whether or not the project can be used as a work reference in proposals; default is N (No)
EstCompletionDate datetime 8 Project's estimated completion date
ActCompletionDate datetime 8 Project's actual completion date
ContractDate datetime 8 Project contract's award date
BidDate datetime 8 Date when the organization submitted its bid on the project
ComplDateComment varchar 20 User-entered comment regarding the completion date
FirmCost decimal 9 Organization's total cost for completing the project
FirmCostComment varchar 20 User-entered comment regarding the Firm Cost
TotalProjectCost decimal 9 Total project cost
TotalCostComment varchar 20 User-entered comment regarding the Project Cost
OpportunityID varchar 32 Project's Opportunity record number; must exist in Opportunity (OpportunityID/Opportunity)
ClientConfidential varchar 1 Variable indicating whether the client's name will be used in proposals or replaced with an alias; default is N (No), the client's name is not confidential
ClientAlias varchar 100 Client alias to use in proposals if the client is confidential
AvailableForCRM varchar 1 Variable indicating whether or not the record is available to CRM users; default is Y (Yes)
ReadyForApproval varchar 1 Variable indicating whether or not the record is available to Accounting users
ReadyForProcessing varchar 1 Variable indicating whether or not the record is approved for use in transaction processing
BillingClientID varchar 32 Client record number for the billing client; must exist in CL (ClientID/Client)
BillingContactID varchar 32 Contact record number for the billing contact; must exist in Contacts (ContactID/(LastName,FirstName,MiddleName,ClientID/Client))
Phone varchar 24 Project location telephone number
Fax varchar 24 Project location facsimile transmission telephone number
EMail varchar 50 Project location email address
ProposalWBS1 varchar 30 Promotional project linked to the record; must exist in PR
CostRateMeth smallint 2 Project's cost rate method
CostRateTableNo smallint 2 Cost rate table number
PayRateMeth smallint 2 Project's pay rate method
PayRateTableNo smallint 2 Pay rate table number
Locale varchar 2 Project's payroll tax locale
LineItemApproval varchar 1 Variable indicating the project's timesheet line item approval setting; valid options are Yes, No, or System (the default)
LineItemApprovalEK varchar 1 Variable indicating the project's expense report line item approval setting; valid options are Yes, No, or System (the default)
BudgetSource varchar 1 This field is active only when BudgetedFlag is set to Error or Warning. The budget to use for budget validation of timesheets; valid options are Project Planning or Budget Worksheet
BudgetLevel varchar 1 This field is active only when the BudgetSource is Project Planning;valid options are Employee Only, Labor Code Only, or Both
ProfServicesComplDate date 4 User-entered value in Prof. Services Compl. Dt. on the project's Background tab; used to auto-populate Part I, block 19 (2) Year Completed - Professional Services of an SF330 proposal
ConstComplDate date 4 User-entered value in Cons. Compl. Dt. on the project's Background tab; used to auto-populate Part I, block 19 (2) Year Completed - Construction of an SF330 proposal
ProjectCurrencyCode varchar 3 Project's functional currency
ProjectExchangeRate numeric 9 The exchange rate for the project's currency. In the Project Info Center, this rate is entered in the Exchange Rate field under the Project Currency field on the Budget & Revenue tab.
BillingCurrencyCode varchar 3 Project's billing currency
BillingExchangeRate numeric 9 The exchange rate for the project's billing currency. In the Project Info Center, this rate is entered in the Exchange Rate field under the Billing Currency fieldon the Budget & Revenue tab.
RestrictChargeCompanies varchar 1 Flag indicating whether or not charges to the project are restricted to named companies; valid options are Y (Yes) or N (No)
RevUpsetLimits varchar 1 Variable indicating whether or not revenue upset limits are enabled for the project
RevUpsetWBS2 varchar 7 Variable indicating whether or not revenue upset limits are enabled at the phase level
RevUpsetWBS3 varchar 7 Variable indicating whether or not revenue upset limits are enabled at the task level
RevUpsetIncludeComp varchar 1 Variable indicating whether or not to include compensation in the project's revenue upset limit
RevUpsetIncludeCons varchar 1 Variable indicating whether or not to include consultant expense in the project's revenue upset limit
RevUpsetIncludeReimb varchar 1 Variable indicating whether or not to include reimbursable expense in the project's revenue upset limit
PORMBRate numeric 9 Reimbursable expense markup for the project's committed expenses from purchase orders
POCNSRate numeric 9 Consultant expense markup for the project's committed expenses from purchase orders
PlanID varchar 32 Internal identifier for the plan record
TKCheckRPDate varchar 1 Flag indicating whether Vision Time should check task start and end dates in Resource Planning