Edit Task Duration

You can edit a task's duration if needed.

To edit a task's duration, complete the following steps:

  1. Access the Schedule page.
  2. Click in the top-left corner of the Job Schedule page to configure the job schedule settings options (optional).
  3. Do one of the following:
    • Hover over the end of the task that you want to change until your cursor becomes a double arrow with a line in the middle (), then click on the end of the task and drag it left or right to increase or decrease the duration.
    • Use the Task Information page:
    1. In the Schedule grid, select the task that you want to edit.
    2. Click to display the Task Info/Staff Allocation sidebar.
    3. On the Task Information page, edit the Start/End Dates.
  4. Click Save.