Match P6 Labor Hours

The MATCH_P6_LABOR_HOURS option on the Preferences dialog box in Open Plan allows you to use the resource assignment level as hours regardless of Open Plan's default duration unit when importing/exporting data to/from Primavera P6.

Since Open Plan still interprets resource units internally in terms of the default duration unit, resource costs on the Activity Progress dialog box may not match costs in P6 unless the Open Plan default duration unit is in hours (when MATCH_P6_LABOR_HOURS = 1).