The date on which an incomplete activity is expected to finish. This date should be on or after Time Now.
The early finish date (and the requested finish date) is equal to the expected finish date if the activity meets all of these conditions:
The activity has the As Planned progress type.
The activity has an expected finish date.
The early start date is before the expected finish.
The expected finish is after Time Now.
The actual start date is blank or beyond Time Now.
An activity with an expected finish date that is before Time Now is treated as complete.
The expected finish date is ignored if it is on or later than Time Now if any of the following conditions exist:
The remaining duration is 0.
The elapsed duration is equal to or greater than the original duration.
The percent complete is 100%.
The Complete option is selected.
The actual finish date is entered.
There are constraint dates on the activity.