Expected Finish

The date on which an incomplete activity is expected to finish. This date should be on or after Time Now.

The early finish date (and the requested finish date) is equal to the expected finish date if the activity meets all of these conditions:

An activity with an expected finish date that is before Time Now is treated as complete.

The expected finish date is ignored if it is on or later than Time Now if any of the following conditions exist:

A new early (and requested) start date is not calculated based on the expected finish and the duration.