External Predecessors and Successors

Predecessor, Successor, and External nodes in the Change Details grid indicate relationships between activities in the selected control account and activities external to the selected control account. The predecessors are listed above the selected control account and the successors are listed below the selected control account.

When you expand the Predecessor node, an External node displays, indicating that the activities below it are external to the selected control account. These predecessor activities drive the start date for activities in the selected control account. When you expand the Successor node, an External node displays, indicating that the activities below it are external to the selected control account. These successor activities can be used to determine what control accounts will have a downstream change, or can be used as a list of handoff activities that occur after the selected control account.

The information for these activities is limited to:

Example of a Change Details Grid with Predecessors and Successors

In the table below, all rows are expanded to display three predecessor activities, followed by the selected control account, followed by two successor activities.

CA

WP

Activity ID

Predecessor

 

 

External

 

 

 

 

1.1.25/06/25.9.6

 

 

2.1.17/02/5.9.17.2

 

 

2.14.7/06/14.7.6.3

 

 

2.25

1.4.6.2

 

 

1.4.6.2

20

 

1.4.6.2

20

1.1.20.2

1.4.6.2

20

1.1.20.3

1.4.6.2

21

 

1.4.6.2

20

1.1.20.4

Successor

 

 

External

 

 

 

 

5.12.4/04/5.12.4.1

 

 

5.12.9/05/5.12.9.5

Relationships Tab

You cannot edit any information on the Relationships tab grid for an external activity.

External Relationships and External Subprojects

If your Open Plan project has external relationships to subprojects, they will not be visible in the Change Details view. Required changes to external information can be made in Open Plan after the change has been applied using the PM Compass Change Requests Add-In before approving the change request.

What do you want to do?

Insert an activity

Add a relationship to an activity

Delay the start of an activity

View activity information

View details of external activities


View location

Learn more about...