Open Plan 8.8 Help

Resource Selection Dialog Box

The Resource Selection dialog box will only appear if specific conditions are satisfied.

These conditions are as follows:

  • A resource file must be assigned to the project.
  • The project must contain at least one activity with resource assignments.

This dialog box controls the resources that are displayed in the histogram.

Note: When selecting resources to display, be sure that all selected resources use the same time unit. For example, you should not mix resources measured in person-hours and resources measured in person-days or person-weeks in the same bar.

A resource categories list allows you to specify the category of resources to be displayed:

  • All Resource Categories
  • Labor
  • Material
  • Other Direct Costs
  • Subcontract
  • Skills

A resource’s category is defined on the General tab of the Resource Details dialog box.


Display the Resource Selection Dialog Box

Use this procedure to display the Resource Selection dialog box

Contents of the Resource Selection Dialog Box

Use the fields and options to configure the Resource Selection dialog box.


Parent Topic:

Tabs and Dialog Boxes