Show Summary Dates on Subprojects
Use this procedure to set Open Plan to display summary dates on subprojects through the Time Analysis dialog box.
To set Open Plan to display summary dates on subprojects:
In the Schedule menu group of the Processes tab, click Time > Options
.On the Options tab of the Time Analysis dialog box, click the Show Summary Dates in Subprojects option.
Click OK.