Create a Relationship (Spreadsheet)
Use this procedure to create a relationship spreadsheet.
To create a relationship in a relationship spreadsheet:
In the Project Views folder of Open Plan Explorer, select a project to display in relationship spreadsheet view.
Select an empty cell in the Predecessor column.
At the right edge of the edit box, click the ellipsis button.
The edit box is the field above the table.
On the Select Activity dialog box, select the activity to become the predecessor in the relationship, and click OK.
In the Successor column, select the activity to become the successor in the relationship using the edit box.
Enter the rest of the information for the relationship.
To create multiple relationships to the same predecessor, repeat this procedure, selecting the same activity ID for each relationship you want to create.
Related Topics
Related Procedures
- Creating a Relationship in a Barchart View Using the Mouse
- Creating a Relationship in a Network View Using a Mouse
- Creating Interproject Relationships in a Network View
- Creating a Link Between Activities
- Removing a Link Between Activities