Change the Work Status of a Day
Use thus procedure to change the status of a day to either Working or Non-Working.
To change the work status of a day:
In Open Plan Explorer, display a calendar.
Take one of the following actions:
- Select the day you want to change, and press the spacebar.
- Right-click the day you want to change, and select either Working or Non-Working from the context menu.