Tabs and Dialog Boxes Related Topics: Add Baseline Dialog Box Use the Add Baseline dialog box to add baselines to the list that is currently displayed in the Baselines dialog box. Baseline Access Control Dialog Box In Open Plan, you can set the security options for a baseline on a project that you have open in either Exclusive or Shared mode. Baseline Date Range Dialog Box Use the Baseline Date Range dialog box to change an activity's baseline dates. Baselines Dialog Box Use the Baselines dialog box to change the currently selected baselines at any time. Copy Baseline Dialog Box Use the Copy Baseline dialog box to create a baseline as a copy of an existing one. Multiple Baselines Dialog Box Use the Multiple Baselines dialog box to select up to three baselines for reporting purposes. You can change these selections at any time. Review Baseline Changes Dialog Box After you make changes in the Update Baseline dialog box, you can preview your changes before they are applied to the project. Select Baselines to Save Dialog Box Use the Select Baselines to Save dialog box to select the baselines to save when you make a copy of the project. Update Baseline Dialog Box Use the Update Baseline dialog box to update an existing baseline, if you have rights to do so. Parent Topic: Project Baselines