Open Plan 8.8 Help

Progress

The progressing function in Open Plan allows you to enter schedule information — actual dates, estimates, and completion status — about activities in a project that is underway.

In addition, you can also enter information about resource usage at the activity level.


Entering Progress Information

In Open Plan, you enter activity progress using the tabbed Activity Progress dialog box. You can display this dialog box by displaying an activity and clicking Progress on the Edit tab.

How Open Plan Uses Progress Information

Once you have entered progress for a project, you can calculate new dates for the activities using either time analysis or resource scheduling.

Entering Physical Percent Complete

Open Plan allows you to progress an activity by entering the physical percent complete (PPC) at either at the activity level or the resource level

Project Progress

You can display project information at any time by opening a project and using the Properties command.

Activity Progress

In general, entering status information about activity progress consists of specifying the related information so that a revised time analysis of the project can be performed.

Resource and Cost Progress

In addition to entering information about the schedule status of activities, you can enter information about resource costs, usage, and forecasts.

Calculating Resource Progress Automatically

If you do not want to enter resource progress manually, you can have Open Plan calculate resource progress automatically based on the current status of the activity.

Calculating Earned Value Progress Automatically

You can have Open Plan update the earned value of the project by selecting the Update Physical Percent Complete option in the Progress Calculations dialog box.

Progress Dates

The Start Date and End Date fields are enabled when you choose to update resource progress or earned value.

Progress Calculations Session Log

Each time you perform progress calculations, Open Plan creates a session log.

Rules For EVT and Activity Physical % Complete

Activity Physical % Complete (PPC) is a percentage estimate of the completed work for an activity.

Tabs and Dialog Boxes

Use the tabs and dialog boxes in this section to manage progress.

Related Procedures

Follow the procedures in this section to manage progress.