Planning Costs
For planners who want to fully utilize Open Plan as an earned value management system, there are a number of features for working with cost information.
These features are as follows:
- You can report on high-level summaries of resource costs based on the resource category or the hierarchy of a resource breakdown structure.
- You can choose which resources to consider in cost calculations.
- You can define escalated and unescalated rates for resources, resource pools, and skills.
Related Topics:
If you want to roll up resource costs into categories, you need to specify the appropriate category for the resource.
For each resource, you should enter a base unit cost. If the resource is a Labor resource, the units are typically hours and the unit cost will be the present value of the direct labor rate.
To define budgets using resources, you must first define the resources in a resource file and then attach the resource file to the project. Then you add resource assignments to the activities.
Open Plan calculates costs and stores them at the detail level, allowing you to store time-phased quantity, cost, and escalated cost by resource and activity.