Field Values and Syntax
Review the fields that are mentioned in Open Plan with their values and syntax, which are useful when you are creating a calculated field or a filter.
For example, if you want to see only activities that have an EVT type set to Steps, you can create this filter: EVT=[EVTE.N].
The tables below list the fields that are mentioned in Open Plan with their values and syntax.
Activity Logic Flag
| Value |
Syntax |
| None |
[LOGI. ] |
| Start Activity |
[LOGI.S] |
| Finish Activity |
[LOGI.F] |
| Start and Finish Activity |
[LOGI.SF] |
| Isolated Activity |
[LOGI.I] |
Activity Status
| Value |
Syntax |
| Planned |
[ACTS.0] |
| In Progress |
[ACTT.1] |
| Complete |
[ACTT.2] |
Activity Type
| Value |
Syntax |
| ASAP |
[ACTT.N] |
| ALAP |
[ACTT.L] |
| Start Milestone |
[ACTT.S] |
| Finish Milestone |
[ACTT.F] |
| Discontinuous |
[ACTT.D] |
| Subproject |
[ACTT.P] |
| Hammock |
[ACTT.H] |
| Effort Driven |
[ACTT.R] |
| External Subproject |
[ACTT.E] |
| Foreign Project |
[ACTT.Z] |
| Foreign Subproject |
[ACTT.Y] |
| Foreign Activity |
[ACTT.G] |
Boolean
| Value |
Syntax |
| True |
[BOOL.T] |
| False |
[BOOL.F] |
Critical Flag
| Value |
Syntax |
| Not Critical |
[CRIT.0] |
| Critical |
[CRIT.1] |
| Most Critical |
[CRIT.2] |
| Controlling Critical |
[CRIT.3] |
Earned Value Technique
| Value |
Syntax |
| Level of Effort |
[EVTE.A] |
| % Complete |
[EVTE.C] |
| 50 - 50 |
[EVTE.E] |
| 0 - 100 |
[EVTE.F] |
| 100 - 0 |
[EVTE.G] |
| User Defined Percentage |
[EVTE.H] |
| Planning Package |
[EVTE.K] |
| Resource % Complete |
[EVTE.L] |
| Steps |
[EVTE.N] |
The following Cobra EVT Types are not included in any Open Plan calculations.
| Value |
Syntax |
| Milestones |
[EVTE.B] |
| Units Complete |
[EVTE.D] |
| Earned As Spent |
[EVTE.O] |
Probability Distribution
| Value |
Syntax |
| Constant |
[DIST. ] |
| Uniform |
[DIST.U] |
| Normal |
[DIST.N] |
| Beta |
[DIST.B] |
| Triangular |
[DIST.T] |
Progress
| Value |
Syntax |
| None |
[PROG. ] |
| Remaining Duration |
[PROG.R] |
| Percent Complete |
[PROG.P] |
| Elapsed Duration |
[PROG.E] |
| Complete |
[PROG.C] |
Project Status
| Value |
Syntax |
| Proposed |
[PRJS.P] |
| Open |
[PRJS.O] |
| Closed |
[PRJS.C] |
Relationship Type
| Value |
Syntax |
| Finish to Start |
[RELT.FS] |
| Start to Start |
[RELT.SS] |
| Start to Finish |
[RELT.SF] |
| Finish to Finish |
[RELT.FF] |
Resource Scheduling Type
| Value |
Syntax |
| Normal |
[RSCL. ] |
| Splittable |
[RSCL.P] |
| Stretchable |
[RSCL.T] |
| Reprofileable |
[RSCL.R] |
| Immediate |
[RSCL.I] |
Resource Class
| Value |
Syntax |
| Labor |
[RESC.L] |
| Material |
[RESC.M] |
| Other Direct Cost |
[RESC.C] |
| Subcontract |
[RESC.S] |
Resource Type
| Value |
Syntax |
| Normal |
[REST. ] |
| Consumable |
[REST.C] |
| Perishable |
[REST.D] |
| Pool |
[REST.P] |
| Skill |
[REST.S] |
Target Type
| Value |
Syntax |
| None |
[TARG. ] |
| Not Earlier Than |
[TARG.NE] |
| Not Later Than |
[TARG.NL] |
| On |
[TARG.ON] |
| Fixed |
[TARG.FX] |