Enter Activity Progress
You can enter activity progress in a barchart or spreadsheet view, or by using the Activity Progress dialog box. This topic describes the steps for all three.
Related Topic
Related Procedure
Related Topics:
This dialog box displays the original duration of the activity along with the current date of Time Now and the current status of the activity.
It is possible to status an activity displayed in a barchart view by manipulating the bar.
When entering progress information using this view, note that the setting of the Progress Type field determines how Open Plan interprets the Progress Value field.