Display the Resource Scheduling Dialog Box
Use this procedure to display the Resource Scheduling dialog box.
To display the Resource Scheduling dialog box for a project that contains resource assignments:
In Open Plan Explorer, select a project.
Take one of the following actions:
- Right-click the selected project, and click Resource Scheduling from the context menu.
- Click the arrow under Resources in the Schedule menu group of the Processes tab, and click Options.
It is not necessary for the project to be open.