Display the Replan Activities Dialog Box
Use this procedure to display the Replan Activities dialog box.
To display the Replan Activity dialog box
In a spreadsheet view, right-click an activity that meets the following conditions:
- It has no child activities.
- Its status is In Progress.
- Its Actual Start date is not blank.
- Its Actual Finish date is blank.
- It is not a foreign activity.
- On the context menu, select Replan Activity.