Calculate Earned Value

Use this procedure to calculate earned value.

To calculate earned value:

  1. Open the project for which you want to calculate earned value.
  2. Take one of the following actions:
    • On the Processes tab, click Cost Calculations.
    • Right-click a project and select Cost Calculations from the context menu.
  3. In the Cost Calculations dialog box, select Earned Values (BCWP and BCWS).
  4. Click OK.
Parent Topic: Related Procedures