Automatically Run Time Analysis for New Activities
Use this procedure to automatically run Time Analysis when you create new activities.
To automatically run Time Analysis for new activities:
Click the File menu and select Preferences > Application.
On the Options dialog box Project tab, select the Calculate dates even if TA is turned off option.
This option requires you to have permission in EPM SA to run Time Analysis.
Related Topics
Related Procedure