Activity Percent Complete Based on Activity Steps
During the Primavera P6 import into Open Plan, progress is set if the Primavera P6 option Activity percent complete based on activity steps is selected.
The table below provides information on how the progress is set.
| P6 Activity Status | Open Plan Progress Type | Open Plan Progress Value |
|---|---|---|
| In Progress | Remaining Duration | P6 remaining |
| Completed | Complete | |
| Not Started | None |