Thresholds Page of the New Code File Wizard
Use the Thresholds page to define acceptable cost and schedule variances.
When a cost variance or schedule variance exceeds the predefined threshold, they are highlighted in either red for unfavorable (negative) or green for favorable (positive). These thresholds, or tolerances, define how large cost variances (Earned Value - Actual Cost) and/or schedule variances (Earned Value - Budget) must be before Cobra triggers exception reporting mechanisms.
Schedule Variance
A schedule variance is a metric for the schedule performance of a project. It is the algebraic difference between earned value and the budget (Schedule Variance = Earned Value - Budget). A positive value is a favorable condition while a negative value is unfavorable.
Field | Description |
---|---|
Current period |
This field refers to the schedule variance for the current period. Use the Favorable and Unfavorable drop-down lists to define tolerances for this field. Your options are discussed in detail below. |
Cumulative |
This field refers to the cumulative schedule variance. Use the Favorable and Unfavorable drop-down lists to define tolerances for this field. Your options are discussed in detail below. |
Cost Variance
A cost variance is a metric for the cost performance of a project. It is the algebraic difference between earned value and actual cost (Cost Variance = Earned Value - Actual Cost). A positive value indicates a favorable position and a negative value indicates an unfavorable condition.
Field | Description |
---|---|
Current period |
This field refers to the cost variance for the current period. Use the Favorable and Unfavorable drop-down lists to define tolerances for this field. Your options are discussed in detail below. |
Cumulative |
This field refers to the cumulative cost variance. Use the Favorable and Unfavorable drop-down lists to define tolerances for this field. Your options are discussed in detail below. |
At complete |
This field refers to the cost variance at project completion. Use the Favorable and Unfavorable drop-down lists to define tolerances for this field. Your options are discussed in detail below. |
Threshold Options
Value | Description |
---|---|
None | The code file does not use thresholds or tolerances. |
Percent | Cobra defines the schedule variance as a percentage amount. |
Value | Cobra defines the schedule variance as an absolute amount. |
Both | Cobra defines the schedule variance using both the percentage amount and the absolute value. |